TYRRELSTOWN PRIMARY SCHOOL

Project:

Client:

Tyrrelstown 500 Pupil School

Glasgiven Contracts

We were contracted to construct the precast building of a new 500 pupil Primary School in Tyrrelstown, Dublin 15.

DCIM100MEDIADJI_0047.JPG
GALLERY
O’Reilly Concrete were contracted to construct the precast building of a new 500 pupil Primary School in Tyrrelstown, Dublin. There was many challenges on site including the SNU unit which required a lot of Cast – ins. Also the PE Hall was constructed using 250 external Precast Walls that could not be lifted normally so a special turning device was used on site. However, ORC met these challenges and it was a very successful project. We were given a programme on site of 20 weeks, however we came in 2 weeks early on the project.

VIDEO CASE STUDY

PRECAST PRODUCTS