Main Contractor: Balfour Beatty
Week 4: Progress on site

Some drone images of Coolock Primary Care Centre which is currently being erected as a precast concrete frame by O’ Reilly Precast Concrete. The frame for this 75,000 sq. ft. building will be fully erected over a 12 week programme and consists of 200mm solid precast walls, precast columns/beams, hollowcore flooring and precast stairs.

Click to view Images

Due to the footprint of the building covering 90% of the overall site, the building is being erected in 3 phases working from the furthermost point towards the site entrance. This significantly reduced the client’s Crane cost by enabling all fitting to be carried out using a 100 tonne crane as opposed to a 300 tonne which would have been required to erect in one phase.

 